Hong Kong Water Supply Shek Pik Reservoir – Part 2 Reservoir Construction

Shek Pik

Tymon Mellor: With continued water shortages on Hong Kong Island and Kowloon, pressure was on the Shek Pik construction team to complete the reservoir as fast as possible. The situation was so bad that during a particularly bad drought in the summer of 1963, the Government hired 13 tankers to ferry water from the Pearl River to a new terminal […]

» Read more

Hong Kong Water Supply – Shek Lei Pui and Kowloon Byewash Reservoir

Kowloon Bywash

Tymon Mellor: With the growing population in both Hong Kong Island and Kowloon there was a growing demand for drinking water, the existing supplies, primarily the Tai Tam reservoirs and Kowloon Reservoir were insufficient to meet such needs. With the failure of the spring rains, water famine became a common occurrence, and a quick fix was required. Water Shortages Following […]

» Read more

Shatin Airfield 1949-1962

Tymon Mellor: Following the Second World War, in 1949 the Royal Air Force established a permanent airfield at Shatin,with a 350m long concrete runway, coordinates 05/23 and a small control tower, along with building and hangars made of corrugated steel. With the growing tension in China, during the 1950’s the British Army Air Corps operated Auster AOP.9 spotter planes from the […]

» Read more

West Rail – Part 6 Project Management

Word Image 74039 1

Tymon Mellor: The West Rail project was completed on time and below budget, this was achieved by having a strong management team, experienced construction managers, motivated contractors and efficient project process. Building a large infrastructure project within existing urban environments is not just about the engineering but it is as much about managing all the different competing requirements, in particular […]

» Read more

West Rail – Part 5 Construction – Southern Section

Word Image 73983 1

Tymon Mellor: With the approval of the environmental impact assessment in March, 1998 and endorsement of the Project Agreement in September 1998, work on the construction of West Rail could commence. The West Rail project management team had already started tendering the key construction packages and with the approval of the scheme, the initial packages were awarded allowing a ground […]

» Read more